    New Buildings Update

    New Building Update

    Our new Year 9 Centre and Multi-purpose Hall are on track to open at the start of Term 3 2019 with the estimated completion date July 31st. The builders, CICG, have been providing us with regular updates and works are progressing well and to schedule.

    Currently CICG are doing the following:

    Year 9 Centre

    • Windows doors and trims ongoing
    • Epoxy floors completion 
    • External Drainage ongoing
    • Carpentry fix ongoing
    • Painting completed
    • Ceilingframingcommenced 

    Multi-purpose Hall

    • Carpentry framing and facades ongoing
    • All services rough in works ongoing
    • Internal lining commenced
    • External cladding ongoing
    • Games Hall Ceiling ongoing
    • Plaster lining commenced

    Work to be undertaken in the next week or so:

    Year 9 Centre

    • Classroom ceilings completed
    • Window frames and glazing completed
    • Carpentry fit off ongoing
    • Pinboards and whiteboards commenced
    • Toilet partitions
    • External pavement commenced

    Multi-purpose Hall

    • Façade cladding ongoing
    • Painting facades ongoing
    • Services rough in works ongoing
    • External Lining ongoing
    • Hall ceiling ongoing

    Further updates will be published as they are supplied.