07 March 2019

New Buildings Update

New Buildings Update

Our new Year 9 Centre and Multi-purpose Hall are on track to open at the start of Term 3 2019 with the estimated completion date July 31st. The builders, CICG, have been providing us with regular updates and works are progressing well and to schedule.

Currently CICG are doing the following:

Year 9 Centre

  • Stopping and sanding ongoing
  • Wall and floor vinyl completed
  • Windows doors and trims ongoing
  • Joinery install completed
  • External Drainage ongoing

Multi-purpose Hall

  • Brick facades completed
  • Carpentry framing and facades ongoing
  • Internal blockwork completed
  • All services rough in works ongoing
  • External cladding ongoing
  • Multi-purpose Hall Ceiling commenced

Work to be undertaken in the next week or so:

Year 9 Centre

  • Internal stopping and wall sanding to be completed
  • Frame all classroom ceilings
  • Window frames and glazing ongoing
  • Painting ongoing
  • Carpentry fix commencing
  • External drainage ongoing.

Multi-purpose Hall

  • Façade cladding ongoing
  • Painting facades commenced
  • Services rough in works ongoing
  • Wall & ceiling framing ongoing
  • External Lining ongoing
  • Hall ceiling ongoing

Further updates will be published as they are supplied.